Commercial/Industrial
Permit
USD's
required permit process:
This process is required
for Commercial/Industrial projects, including new building construction,
additions, expansions and tenant improvements
- Submit complete plans for review. USD will only review complete
plan submittals (see below)
- During the initial review, USD will estimate plan check fees
based on the total estimated sewer construction cost and will
generate a fee schedule
- Plan review fees are due after the first review, upon pickup
of plan review comments
- Each plan review submittal can take up to 10 business days to
complete. Submittals are reviewed on a first-come, first-served
basis
- For any industrial waste discharge, a separate permit must be
obtained by the discharger of the industrial wastes, prior to
approval of plans or issuance of a building sewer construction
permit
- If no major changes are required, USD will approve the drawings
for construction. This approval is not a permit
for construction. If changes are required, drawings must be revised
and resubmitted for review until USD approval is obtained
- USD will calculate fees for: Permit, inspection, any capacity/connection,
and any work to be performed by USD crews
- For new buildings on previously vacant lots, or an increase
in floor area/addition to an existing building, additional capacity
fees may be required. Please see the Connection
Fees page for current rates
- All contractors wishing to obtain sewer construction permits
for work in the Union Sanitary District must present evidence
of current California Contractors license, Workers Compensation
insurance, and General Liability insurance with Union Sanitary
District as an additional insured
- Upon payment of all fees and evidence of a city building permit,
a sewer permit may be obtained by the party contracted to do the
underground construction
- Three sets of cut sheets must be submitted to USD for review.
Blank
cut sheets and Cut
Sheet Instructions are provided here
- Call 24 hours before beginning sewer construction to schedule
inspection
USD's
requirements for complete plan submittal:
See Commercial/Industrial
Plan Submittal Requirements for additional details
- Request
for Plan Check form
- Three copies of the civil site plans
- For commercial kitchens, three sets of kitchen equipment plans
are required
- One copy of the architectural floor plans
- Digital Submittal